Real Time Systems - Old Questions

10. Define busy interval. Calculate the busy interval for task T1(2,1), T2(3,1,25) and T3(5, 0.25) over the interval (0, 12) schedule through the Rate Monotonic (RM) algorithms.

8 marks | Asked in 2074