Software Project Management - Old Questions
2. The table below is an example of project specification with estimated activity duration and precedence requirements:
Activity Name | Activity Name | Duration (Weeks) | Precedents |
A | Hardware Selection | 6 | |
B | System Configuration | 4 | |
C | Install Hardware | 3 | |
D | Data Migration | 4 | A |
E | Draft Office Procedures | 3 | B |
F | Recruit Staff | 10 | |
G | User Training | 3 | E,F |
H | Install and test system | 2 | C,D |
10 marks
|
Asked in Model