Software Project Management - Old Questions

2. The table below is an example of project specification with estimated activity duration and precedence requirements:


Activity Name
Activity Name
Duration (Weeks)
Precedents
AHardware Selection
6
BSystem Configuration
4
CInstall Hardware
3
DData Migration
4A
EDraft Office Procedures
3B
FRecruit Staff
10
GUser Training
3E,F
HInstall and test system
2C,D


Find the critical path of the project and calculate the earliest completion time of the project.
10 marks | Asked in Model